Document the field inventory, current behavior and acceptance tests before replacing an older control system.
Document the existing system
Verify I/O lists, drawings, safety chains and operator steps on site. Do not assume unknown signals are irrelevant.
Plan cutover and rollback
Run scenarios on a bench or in simulation first. Include downtime, labels and rollback conditions in the plan.